Status Reports are filed by the team member/assignee from within Microsoft Outlook or the EasyTaskLink task detail. It is recommended that the status report be filed from within the task detail because this provides a place to make a comment on the period’s progress on the task. Even if no progress was made it is valuable to provide an explanation on what is holding up the task. This information may seem insignificant at the time, but provides an invaluable tool when there is a problem down the line. We leave this up to the Project Manager’s discretion.
There are two ways for Workgroup/Enterprise team member files a status report:
1. From Outlook Tasks Folder, or
2. From EasyTaskLink Interface (use the task detail toolbar button).